Ramganjmundi - Bhopal railway line project

WCR is implementing the Ramganjmundi – Bhopal new BG railway line project. As per the December, 2019 work status report, the passenger train has started running between Ramganjmandi – Jhalawar. The formation work beyond Jhalawar is in progress. Land acquisition is completed beyond Jhalawar city upto km 109. The reply is awaited from Govt. of Rajashtan & MP for sharing the cost of the project beyond Jhalawar. The original completion date was March, 2021, but as per the estimation, the project is likely to complete by March, 2023.

Location: Jhalawar Rajasthan

Estimated Value (Rs. Cr): 424.6

Sector: Railways

Project Stage: Under Implementation