Maintenance work of boiler at Obra TPS
Annual Running Breakdown Maintenance work of coal and oil burners air nozzle assembly and Main Boiler, etc, for unit no 9, 10 and 11 of 3x200 MW BTPS Obra. The…
Project leads for your business
Annual Running Breakdown Maintenance work of coal and oil burners air nozzle assembly and Main Boiler, etc, for unit no 9, 10 and 11 of 3x200 MW BTPS Obra. The…
Work contract for annual routine maintenance of non pressure part of boiler and its auxiliaries including maintenance of high pressure valve and lines of 1x500MW unit no. 5 at SGTPS,…
Work contract for annual preventive /breakdown maintenance of non-pressure parts of boiler and its auxiliaries for unit no. 1 to 4 of 210 MW of PH-I and PH-II at SGTPS,…
Cleaning and removing of silt, ash, sludge, etc from boiler / ESP areas and effluent pits of D.M. plants at KTPS. The contract duration is 730 days. The bid due…
WIBDCL plans to undertake the development of Integrated Manufacturing Cluster (IMC) under Amritsar Kolkata Industrial Corridor (AKIC) Project at Raghunathpur, Purulia, West Bengal.
KIADB is seeking extension of validity of terms of reference (TOR) from the environment clearance authority towards the establishment of Devakothikoppa Industrial Area.
Remaining Life Assessment study tests of Boiler of unit no 4, 2x500MW BTPS Anpara. The bid submission deadline is 24/05/2021. (Tender ID: 2021_RVUNL_583245_1).
Amara Raja Batteries, has recently opened advanced lithium-ion technology research hub at its Tirupati unit in Andhra Pradesh. The research hub is likely to become the countryÂ’s first lithium-ion cell…
Supply of Helium Gas as per requirement. The bid submission deadline is 30/04/2021. (Tender ID: 2021_SINP_598176_1)